What are plant losses costing you today?

Enter your own figures. You'll see the estimated annual loss, an improvement scenario based on your assumptions, and every formula used.

Your figures

Example values: replace them with your plant's.

Operation
Unplanned downtime

Labor and fixed costs you keep paying, plus the margin on lost output.

Scrap and rework

Out-of-spec, held or reworked product.

Manual record-keeping

Counting, transcribing sheets, building reports.

Wages plus payroll taxes and benefits.

Improvement scenario

How much of each loss you believe could be reduced. It's your assumption: only measurement confirms it.

Investment

Optional. Only used to calculate payback.

Subscription, support.

Estimated annual loss: $76,500. Potential annual savings: $18,875.

Your estimate

Estimated annual loss

$76,500

50 production hours lost to stops per year

Unplanned downtime
$60,000
78%
Scrap and rework
$12,500
16%
Manual record-keeping
$4,000
5%

Potential annual savings

$18,875

Based on your reduction assumptions. Illustrative.

Investment payback

Enter an investment to calculate payback.

Review these numbers with a specialist
How it's calculated
  1. Unplanned downtime = 4 stops/wk × 15 min × $20/min × 50 wk = $60,000
  2. Scrap and rework = $250/wk × 50 wk = $12,500
  3. Manual record-keeping = 10 h/wk × $8/h × 50 wk = $4,000
  4. Potential annual savings = $60,000 × 25% + $12,500 × 15% + $4,000 × 50% = $18,875

What this estimate is

  • It uses only the figures and assumptions you entered.
  • It's not a result from Autech or any customer.
  • A saving is only confirmed by measuring: a baseline at the start and the same measurement afterward.
  • The real investment depends on the technical design of your line.

Let's start with one problem.

Tell us what's costing you most today. We'll review it with you, show how we'd solve it and estimate its value together.